Optimization of Chemical Equipment Facilitates Additional Product Worth $1.9 Million Profit
Project Background
A major specialty chemical manufacturer had spent a substantial amount of capital to develop and optimize four polymer reactor systems and achieved the individual reactor performance expected; however, when operated concurrently, the reactors could not achieve optimized rates without overloading a shared distillate recovery system. Instead of operating at full production capacity and creating a costly waste stream, the reactors were operated at 90% of their new capacity.
Due to competing company priorities, internal resources could not be assigned to address this operating bottleneck immediately, even though the return potential was very high.
IPM’s Solution
Integrated Project Management Company, Inc. (IPM) was requested to manage the activities associated with upgrading the distillate recovery system and removing this production bottleneck. IPM was selected for this assignment because of past project performance and its unique ability to organize and lead client teams to achieve an objective efficiently.
To ensure project requirements and success criteria were understood, IPM assembled a project team consisting of client team members representing the Marketing, Environmental, Production, Operations, Maintenance, Process Engineering, and Production Engineering. Once the project requirements were defined, IPM used the requirements to manage the services of an external process equipment design company and developed a viable concept design.
During the design phase, additional instrumentation was installed to analyze the process and the distillation system was modeled. While optimizing the recovery process, the team identified a waste stream that was sufficiently refined to become a marketable product. This potential was explored further and validated to be worth substantial investment. The process modeling requirements were adjusted and the design optimized with this added goal. The result was a modification plan that would increase the throughput rate of this distillation system to remove the production bottleneck and convert a previous waste stream into saleable product.
After the column modification plan was approved, IPM planned and implemented the modifications.
Project Results
The modification plan was implemented on time and within budget, and the distillate recovery system performed as modeled and planned. Further testing and tuning of the system, led by IPM’s project manager, demonstrated that the system could operate at 115% of the optimized reactor production rate.
According to the superintendent of this production area, the results of this project have provided the ability to produce additional product worth $1.9MM in net profit. Furthermore, one of the previous waste streams from this system now met the quality specifications to be considered a saleable fuel, and the ongoing disposal cost of that waste stream was replaced with positive cash flow.
The collaboration brings together IPM’s business process and manufacturing improvement expertise and Phenix Software’s cloud-based scheduling solution that bridges the gap between planning and execution.…
By Jason Bonnet, Managing Director, Consumer Products, Integrated Project Management Company, Inc. It’s no secret that today’s economic environment and consumer spending habits demand that…
CURT Manufacturing, a trailer hitch manufacturer based in Eau Claire, Wisconsin had a vision to optimize its 150,000 square foot manufacturing plant, and fast. The…
Not all construction problems involve projects that are running behind schedule. Jobs that are beating the clock can be just as disruptive, especially when construction…
Project Background As a result of aggressive business growth through acquisition, a global provider of design-coordinated surfacing solutions to residential and commercial customers suffered from…
A major food company was experiencing problems with its direct store delivery (DSD) operations. The distribution network consisted of more than 100 company-owned and/or -operated…
Which impact you the most? Complexity in a manufacturing enterprise is the new reality. In addition to everyday activities, you’re tasked with driving out costs,…